Which of the following is NOT an advantage associated with a mature project management office (PMO)?
Correct Answer Explanation
A mature PMO provides historical data, coordination, and governance visibility across all projects. Independent projects that operate outside the PMO create risk by removing organizational visibility and control — they are a disadvantage, not a benefit.