Home MCQs CISA Question #1756
Back to Questions
CISA QUESTION #1756
Question 1
Which of the following is NOT an advantage associated with a mature project management office (PMO)?
  • Advanced planning assistance
  • Master project register
  • Coordination of projects across departments
  • Independent projects✔️
Correct Answer Explanation
A mature PMO provides historical data, coordination, and governance visibility across all projects. Independent projects that operate outside the PMO create risk by removing organizational visibility and control — they are a disadvantage, not a benefit.