Which category of BPR risks is most likely to emerge during the design phase?
Correct Answer Explanation
The primary risks during the BPR design phase are improper scope definition, lack of required skills, political resistance from stakeholders, and insufficient management support — collectively categorized as scope risk, skill risk, and political risk.