Back to Questions
Civil Engineering
QUESTION #2133
Question 1
The critical path in a CPM (Critical Path Method) network is defined as:
Correct Answer Explanation
The critical path is the longest duration path through the project network from start to finish. It defines the minimum possible project duration. Activities on the critical path have Total Float (TF) = 0: TF = Late Start − Early Start = Late Finish − Early Finish. Any delay to a critical activity delays the entire project by the same duration. Non-critical activities have positive float — they can be delayed without affecting project completion.
Sign in to join the conversation and share your thoughts.
Log In to Comment