In Critical Path Method (CPM), which activity characteristic determines the project completion time?
  • Activities with highest cost
  • Activities on the critical path✔️
  • Activities with most resources
  • Activities with earliest start
Correct Answer Explanation
The Critical Path consists of activities with zero slack/float time. Any delay in these activities directly delays project completion. Activities not on the critical path have slack and don't affect overall duration if delayed within their float.