Back to Questions
SSC Financial and Cost Accounting P-1 QUESTION #6152
Question 1

Cutting department data — Budget: Overheads $40,000; Machine hours 2,800; Labour hours 2,600. Actual: Overheads $44,000; Machine hours 2,700; Labour hours 2,900. What OAR would have been used?

  • $14.29 per machine hour
  • $15.17 per labour hour
  • $15.38 per labour hour✔️
  • $16.30 per machine hour
Correct Answer Explanation

Option C ($15.38 per labour hour) is correct.

OAR uses budgeted figures: $40,000 ÷ 2,600 budgeted labour hours = $15.38 per labour hour.

Labour hours are the more appropriate basis as actual labour hours (2,900) exceed actual machine hours (2,700), indicating a labour-intensive department.