When calculating the Net Present Value of a 5-year project, if the discount rate increases, what happens to the NPV?
Correct Answer Explanation
Because the discount factor $(1+i)^n$ is in the denominator, a higher $i$ results in a lower Present Value of future cash flows, thus decreasing NPV.