Question 1
In a risk-based audit approach, an auditor must choose between auditing a low-risk system with known minor issues or a high-risk system with uncertain status. Which decision BEST reflects risk-based methodology?
Correct Answer Explanation
Risk-based auditing prioritizes resources toward highest-risk areas with greatest potential impact. Uncertain status in a high-risk system represents significant potential exposure that must be investigated. Known minor issues in low-risk systems, while needing attention, pose less organizational threat.