An organization conducts business impact analysis and assigns Recovery Point Objective (RPO) of 1 hour but performs full backups only weekly with no incremental backups. What is the MAXIMUM potential data loss?
Correct Answer Explanation
RPO defines maximum acceptable data loss, while backup frequency determines actual potential data loss. Weekly backups mean up to 1 week of data could be lost in a disaster. The gap between 1-hour RPO requirement and weekly backup capability represents a critical mismatch between business requirements and technical implementation.