Public Procurement Rules, 2004 QUESTION #1795
Question 1
According to Rule 19(1)(c), a bidder who fails to abide by a bid securing declaration — but without involvement in corrupt or fraudulent practices — shall be blacklisted and cross debarred for a maximum period of:
  • Six months✔️
  • One year
  • Two years
  • Three years
Correct Answer Explanation
Rule 19(1)(c) prescribes that a bidder who fails to honor a bid securing declaration, but is not found guilty of corrupt or fraudulent practices, shall be blacklisted and cross debarred for a period not exceeding six months.