Public Procurement Rules, 2004
QUESTION #1799
Question 1
Under Rule 25, the maximum permissible bid security that a procuring agency may require from bidders is:
Correct Answer Explanation
Rule 25 (as inserted via S.R.O. 834(I)/2021) stipulates that a procuring agency may require bidders to furnish a fixed amount of bid security not exceeding five percent of the estimated value of the procurement as determined by the procuring agency.