Public Procurement Rules, 2004 QUESTION #1801
Question 1
Under Rule 26(3), if a bid validity extension is considered necessary, the maximum extension that may be granted shall not exceed:
  • Fifteen days
  • Thirty days
  • A period equal to the original bid validity period✔️
  • Sixty days
Correct Answer Explanation
Rule 26(3) specifies that under exceptional circumstances, where an extension of bid validity is considered necessary (with reasons recorded in writing), the extension shall be for not more than a period equal to the period of the original bid validity — regardless of the actual duration.