Under Rule 26(3), if a bid validity extension is considered necessary, the maximum extension that may be granted shall not exceed:
Correct Answer Explanation
Rule 26(3) specifies that under exceptional circumstances, where an extension of bid validity is considered necessary (with reasons recorded in writing), the extension shall be for not more than a period equal to the period of the original bid validity — regardless of the actual duration.