Public Procurement Rules, 2004 QUESTION #1803
Question 1
Rule 35 requires procuring agencies to announce the final bid evaluation report at least how many days prior to the award of a procurement contract?
  • Seven days
  • Ten days
  • Fifteen days✔️
  • Twenty-one days
Correct Answer Explanation
Rule 35 (as substituted via S.R.O. 834(I)/2021) mandates that the procuring agency announce the result of bid evaluation in the form of a final evaluation report, with justification for acceptance or rejection, at least fifteen days prior to awarding the procurement contract.