Under Rule 13(1), what is the minimum response time for international competitive bidding from the date of publication of the advertisement or notice?
Correct Answer Explanation
Rule 13(1) sets a minimum response time of fifteen days for national competitive bidding and thirty days for international competitive bidding from the date of first publication of the advertisement or notice, with no time limit applicable in cases of emergency.