Public Procurement Rules, 2004
QUESTION #1805
Question 1
According to Rule 16A(4), what is the maximum duration permitted for an open framework agreement?
Correct Answer Explanation
Rule 16A(4) inserted via S.R.O. 442(I)/2020 specifies that open framework agreements shall have a maximum duration of not more than three years, while closed framework agreements shall not exceed one year in duration.