Basic Mathematics QUESTION #2903
Question 1
A can do work in 6 days, B in 12 days. Together they take:
  • 3 days
  • 4 days✔️
  • 5 days
  • 9 days
Correct Answer Explanation
Combined rate $= 1/6 + 1/12 = 3/12 = 1/4$. Thus, $4$ days.