If 10 men can complete a work in 20 days, how long will 8 men take to do the same job at the same rate?
Correct Answer Explanation
Using the work formula: Men × Days = constant
\(10 \times 20 = 8 \times d \Rightarrow d = \dfrac{200}{8} = 25\) days
\(10 \times 20 = 8 \times d \Rightarrow d = \dfrac{200}{8} = 25\) days